PI Requirements
please see CPP Policy 1206
- Registering an online Intent-to-Submit with ORSP: AT LEAST 30 days prior to the sponsoring agency submission deadline.
- **Please note that if the submission is as a subaward, this 30-day requirement applies to the date for documents required by the Prime institution which normally precedes the Sponsor deadline.
- Submitting documents for approval routing: 2 weeks (10 business days) prior to the submission deadline. Documents include:
- final budget (including budgets for any subcontracts)
- final budget justification
- draft proposal abstract
- statement of work (SOW)
- Final proposal documents: 1 week (5 business days) prior to submission deadline