Switch Pad Installation Near Cedritos Residence Hall to Start on Monday, Feb. 15
Summary of Disruption: The Electrical Infrastructure Upgrade (EIU) Project contractor will install an electrical switch pad near Cedritos Residence Hall (Building 58) starting on Monday, Feb. 15. The work will be performed on weekdays from approximately 7 a.m. to 3:30 p.m. The site will be fenced off and installation is scheduled to be completed by the end of February.
Reason for Disruption: Allow EIU contractor crews to start installing the new electrical system.
How does this affect me? University Drive, sidewalks and crosswalks will remain open.
What do I need to do? Pedestrians and drivers are urged to use caution when approaching the work area. Please share this information with others who may have not received this message.
For any questions or more information, please contact: Chi Kwan Fong, senior project manager, at (909) 378-0399 or Ext. 4062, and Chris Norris, lead electrician, at (909) 238-6831 or (909) 997-6467.