Sidewalk Near Camphor Lane and Olive Lane Walk to Undergo Restoration Starting on Monday, July 26
Summary of disruption: The Electrical Infrastructure Upgrade (EIU) Project contractor will restore a section of sidewalk on Camphor Lane near Olive Lane Walk starting on Monday, July 26. The work will be performed on weekdays from approximately 7 a.m. to 3:30 p.m. and is expected to be completed by Monday, Aug. 16.
Reason for disruption: Allow EIU contractor crews to install the new electrical system.
How does this affect me? Pedestrians should follow detour signs around the work site.
What do I need to do? Drivers of campus vehicles and pedestrians are urged to use caution when approaching the work area. Please share this information with others who may have not received this message.
For any questions or more information, please contact: Bruyn Bevans, Senior Project Manager, at (909) 979-5517 or Chris Norris, lead electrician, at (909) 238-6831 or (909) 997-6467.