Driveway Trenching Near Student Health Center to Start on Friday, Dec. 4
Summary of Disruption: The Electrical Infrastructure Upgrade (EIU) Project contractor will trench the parking lot driveway near the Student Health Center (Building 46) starting on Friday, Dec. 4. The work will be performed on weekdays from approximately 7 a.m. to 3:30 p.m. The site will be fenced off and the work is expected to be completed by mid-December.
Reason for Disruption: Allow EIU contractor crews to start installing duct banks.
How does this affect me? A section of the parking lot driveway will be open for access. Four parking spaces adjacent to the lot entrance will be temporarily closed.
What do I need to do? Drivers and pedestrians are urged to use caution when approaching the work area. Please share this information with others who may have not received this message.
For any questions or more information, please contact: Chi Kwan Fong, senior project manager, at (909) 378-0399 or Ext. 4062, and Chris Norris, lead electrician, at (909) 238-6831 or (909) 997-6467.