Campus Electrical System to Be Shut Down for 4 Hours on Monday, Dec. 28
Summary of Disruption: The Electrical Infrastructure Upgrade (EIU) Project contractor will shut down the campus electrical system from 6 a.m. to 10 a.m. on Monday, Dec. 28. All campus buildings will not have power. Facilities electrical crews will be on stand-by to re-start the system.
Reason for Disruption: Allow EIU contractor crews to perform inspections services for the new electrical system.
How does this affect me? Elevators will not be operable during the shutdown. Use stairwells in buildings. Before the shutdown, turn off computers and other electrical devices.
What do I need to do? Please share this information with others who may have not received this message.
For any questions or more information, please contact: Chi Kwan Fong, senior project manager, at (909) 378-0399 or Ext. 4062, and Chris Norris, lead electrician, at (909) 238-6831 or (909) 997-6467.